  1. If a SD-ticket has status 'In Progress'   Req. SQL Elevated user rights can be requested  by selecting this option via the Workflow button.
  2.  A new authorization request ticket is created (linked as 'implements' to the original user ticket).
    Status of the original ticket changes to 'Pending Linked ticket execution'

  3. The assignee opens this ticket and enters
    1. a reason for access in the description field.
    2. Specifies the Admin account
    3. Specifies the Instance, remove the non relevant options.
    4. Specify the database name
    5. Specifies the access required, remove the non relevant options.



  4. Select Req. Authorizations via the Workflow button.


  5. This request is published on the Teamlead / Department Manager project management board for approval, status changes to Awaiting authorization.


  6. Approver selects: 'Approved INFRA-SDENGINE'


  7. Once approved, Status changes to Awaiting execution and Yamaha team: INFRA-SD ENGINE is added. 

    The ticket is moved to the INFRA-SD  dashboard to grant the access and inform the assignee. 
     

  8. After access is granted Infra-SD team ENGINE closes the ticket.

    Resolution will automatically be set


  9. The original linked ticket status is transferred back to 'In progress' after elevated user rights have been granted.
    .

...