Ideally, the amount of tickets in progress simultaneously is low, showing that the team is able to focus.

A rising trend line is means that the team is increasing their WIP and is a warning sign for the team.

The Cycle Time Trend breaks work done up into 2-week periods, and shows the average amount of days the tickets solved in that period took.

On the right hand top the average for the entire quarter is shown.

A rising trend line means that the team is increasingly taking longer on average to solve their tickets and is a warning sign for the team.

The Kanban Velocity breaks work done up into 2-week periods, and shows the amount of items solved within each period.

On the right hand top the average solved per two weeks over the entire quarter is shown.

A dropping trend line means that the team is steadily decreasing the amount of tickets they solve over time and is a warning sign for the team.

The Backlog Readiness shows what the Definition of Ready is for open items in this team's backlog.

This is measured by counting the field "DoR" present on all YIS tickets. SD tickets will show in this graph as "None".

Ideally a team has all items in process at the stage "ready for sprint", and roughly an equal amount at "acceptance criteria defined" (ready for next period).

Image AddedImage Removed