- Component's: Predefined set of labels, Component YNS is automatically added upon creation of an YNSEU Issue.
- Phase: Used to indicate to which Project Phase this issue belongs to
- Workstream: Used to distinguish which project items are linked to and is mandatory to be filled in ANY issue type
- Dependent Workstream: Used to distinguish which project items are linked as 'secondary workstream' and to specify dependencies
- Yamaha Team(s): Yamaha Team is a multi select drop down field which is used to indicate which team is involved for this issue and to have the issue reflected on the teams Dashboard or Board.
- YNS Deliverables: Used to indicate to which stage of Deliverable this issue is part of
- Decision Type: Single select list, to indicate the Decision type, is only applicable for issue type Decision
- Target start: Planned start date when a team will start working on the issue. Used in Advanced Roadmap Plans. To be filled by YNS Workstream lead, YNS PMO or PO.
- Target end: Planned end date when a team will complete the work on the issue. Used in Advanced Roadmap Plans. To be filled by YNS Workstream lead, YNS PMO or PO.
- Baseline start date: Read only field. Used to indicate original planned start date, will be set automatically when for first time target start is set. Not applicable for issue type Decision
- Baseline end date: Read only field. Used to indicate original planned end date, will be set automatically when for first time target end is set. Not applicable for issue type Decision
- %Completion: Completion percentage for YNS work.
- Final Decision: Multi line Text field to capture the final decision for issue type Decision. This is mandatory to be filled when closing a Decision.
...