Jira/Confluence roadmap 2023

Roadmap is up to date In Advanced Roadmaps,: https://support.yamnet.com/secure/PortfolioPlanView.jspa?id=8&sid=8&vid=32#plan/backlog
Filter on Yamaha team: JIRA-APPS



ApplicationSubjectJira IssuePlanningStatusCurrent situation
GeneralAFOS migration Jira/Confluence/Bitbucket

 Q1, Q2

Migration to AFOS checklist

  • Contract for hosting and service in private cloud pending at Avisi, this needs to be ready before Go live can be set.
  • DPA/DPIA pending at Yamaha
  • DPA pending at Avisi
  • Jira: almost ready, outstanding: e-mail and SAML configuration
  • Confluence: ready
  • Bitbucket: awaiting on Avisi for environment setup

Project canceled.

GeneralServicedesk redesign including portal (Jira SD project)

Q3/Q4
Q1 2024

Q3/Q4 alignment
Q1 2024 configuration

GeneralYMES use Jira/Confluence Service management project including support portal or different project setup?

Q2, Q3

Preparation start Q2, 13-04-2023 meeting with Eva Bonilla and other YMES  stakeholders 
Sprint: '23 Jira apps -S15 started 05/Jul/2023 - planning to finalize in '23 Jira apps - S20  September 2023

GeneralYME (Technical) Service Division, New Jira Service management project including support portal

Q4

Intro meeting with team has taken place.

GeneralLicense renewing Jira/Confluence/Bitbucket including addons. Most licenses expire March 2023 and some in June/July 2023. Licensed need to be requested before the end of January 2023 at Avisi. 

Q1 

Licenses renewed for 1 year, new expire date 16-03-2024

GeneralSSO Setup and new ADFS user sync for Jira, Bitbucket, Confluence (SAML addon)

Q2
Continue Q4

SSO Jira in TEST environment, in TEST
SAML ADFS User Sync configuration  Test environment IN PROGRESS but cannot be used, not all fields cannot be retrieved.
Extend usage of Active Directory sync addon. License has been renewed.
User sync active in test and production via Active directory sync

GeneralTwo factor authentication

Q3, Q4

Support partner required to give advice on SAML addon and setup. On hold until September 2023

Jira P&A Customer Support Service management project including support portal

Q1

P&A Customer Support project (PACS)
26-01-2023 all Customer forms live, Users trained and Training material available. 

JiraJira Addons to be discussed, for example usage of BigPicture  and Advance Roadmaps or use different addon for resource planning/roadmap (also to be discussed further with Bjorn/Mohamed)

Q3

Information provided to PMO team:

Big Picture license expires on 15-03-2023 one year  renewal USD: $ 9.400,00 / € 9.063,29
Jira Roadmaps is bundled with Jira Software Data Center and does not require additional licenses.

Site including comparison information for Big Picture, Advanced Roadmaps
https://bigpicture.one/bigpicture-jira-portfolio/
https://bigpicture.one/bigpicture-jira-align-portfolio-aha/

Big Picture information: https://wiki.bigpicture.one/doc/all

Advance Roadmaps information: https://www.atlassian.com/software/jira/features/roadmaps?tab=advanced

Currently Advanced Roadmaps investigated if this could work for IS division.

JiraJira Align Usage? To be discussed for PMO planning.


Q2

Jira Align will not being implemented the coming year, to expensive/advanced for current phase in Agile Transformation.
First explore available options for Big Picture / Jira Advanced Roadmaps.

JiraJira ISMS project for (recurring) tasks and policy and procedure development

Q1, Q2, Q3

ISMS Project created, working on Configuration in close collaboration with Harold Renssen
Recurring task automation has been setup.

JiraNew Jira Project for Compliance, archive Jira-Project IA.

Q3

Project YME Compliance-CMP created waiting on final confirmation form Compliance if Project IA can be archived.

JiraSupport agile teams in usage of Jira and finetuning YIS project.

 

Q1, Q2, Q3, Q4

Continues support during Agile transformation 

  • Formation of new teams , team setup, board setup, YIS introduction
  • Finetune YIS configuration 
JiraSupport Infra- agile teams in usage of Jira and finetuning YIS project.

Q1, Q2, Q3, Q4

Continues support during Agile transformation 

  • Cloud-Rangers team started working in YIS
  • Infra Board is being setup, discuss with team to work with YIS
JiraMigrate Jira development projects YM, BA, BI to YIS




Q1, Q2 ,Q3,Q4

  • Migration of YM to YIS completed, outstanding issues moved. OMS move issues will remain. 
  • Migration of BL to YIS completed, one issue BL-3025 remaining. Project can be archived after J-Sox evidence collection.
  • Migration BA to YIS: Completed Project can be archived after confirmation from Lightbeam team
  • B2C, Yamaha Agile teams moved items to YIS. Other teams remain working in B2C. Alignment in progress to improve B2C project.
    Q3/Q4:
    All B2C teams need to be moved to working in YIS
JiraMigrate Jira development project B2C to YIS




Q1, Q2 ,Q3,Q4

B2C, Yamaha Agile teams moved items to YIS. Other teams remain working in B2C. Alignment in progress to improve B2C project.
Q3/Q4:
All B2C teams need to be moved to working in YIS

Jira Agile- Portfolio (YPB) Initiative structure,  including Board

Q2,Q3

Project YPB configured
Board Initiative in progress

JiraJira/Confluence onboarding/ training 
  • Basic training material
  • Contact YME L&D to centralize training (video's?)
  • Include Jira/Confluence introduction in Onboarding process of new employees, contingent workers.

Q1, Q2, Q3, Q4

Creation of Basis training material : In progress under Space: Atlassian
Jira training







Jira(EU) YNS project support, Backbone Sync - continues support and troubleshooting

Q1, Q2, Q3, Q4

Continues support for troubleshooting Sync errors and new user registration
Setup of EUYNS-YIS sync

JiraJira permissions -> move to authorization per role and groups for global permissions?
Introduce Agile roles

Q3, Q4

Can only being started after finalizing Agile transformation, new roles

JiraJira project cleanup for field configurations and screens

Q1, Q2, Q3, Q4

YIS Cleanup in progress

PMO Cleanup started

JiraAlignment Jira usage IS-Business forward requests between projects?

Q2, Q3

IT <-> Ecommerce
IT<->  P&A Customer Support (PACS) 

JiraUser Onboarding process (including alignment HR, Facility, reception)


Q1

Onboarding procedure is aligned, Jira Process and configuration in place. Released on 1-4-2023.

JiraUser Offboarding process (including alignment HR, Facility, reception)


Q3,Q4

Check with team engine when they are ready to start with setting up this process

JiraUser Application request access process (including Admin request rights)

Q3, Q4

  • Admin request form created and live on portal






ConfluenceConfluence onboarding/ training 
  • Basic training material
  • Confluence introduction in Onboarding process of new employees, contingent workers.

Q3, Q4

Creation of Basis training material under Space: Atlassian
Confluence training

ConfluenceRe-organize IS Confluence spaces

Q1, Q2, Q3, Q4


ConfluenceSimplify permissions and introduce space owners

Q2, Q3, Q4

Space Owners are being appointed and added to the Space description.
https://support.yamnet.com/confluence/spacedirectory/view.action

Simplify permissions step 2. Will already being done for new Spaces. 3 levels: RO,RW and SEC. SD can be requested to add members to the groups.

ConfluenceUser Manuals (Public) Space redesign, include permissions redesign (distributors, YME, third parties, dealers etc.)
Redesign based upon product instead of division/department

 

Q4








BitbucketBitbucket onboarding/ training 
  • Basic training material
  • Onboarding procedure for Bitbucket creation of new project, repositories

Q4

Creation of Basis training material under Space: Atlassian



Jira/Confluence roadmap 2024

GeneralYME Facility Division, New Jira Service management project including support portal

Q1

Intro meeting with team has taken place.

GeneralYME Logistics, New Jira Service Management project including support portal and maybe a Jira Software or Business Project as well for Project tracking 

Q2

Waiting on further input of Logistics

GeneralMigrate Jira/Confluence/Bitbucket to Yamaha AWS environment


TBD

Impediment: support required from Support Partner

GeneralServicedesk redesign including portal (Jira SD project)

Q3/Q4
Q1 2024