Table of Contents | ||
---|---|---|
|
In this chapter below the Jira setup for Yamaha Motor Next Stage project (YNS) is explained.
...
YME will maintain all work done for all EU rollout Project in Jira. To prevent double maintenance in two systems addon Backbone Sync is used to sync YNS project between Jira PwC US Jira and Jira YME.
The issues synced between both instances are limited to EU Rollout Projects only.
Jira Project name in both instances is similar: Yamaha Motor Next Stage project (YNS)
...
01_YNS_JIRA_ProjectManagementPolicy_EN_v1.08 (1).pptx
In JIRA, the main person in charge and sub-person in charge will be assigned to each task.
Software Development within YME is done in project Yamaha IS Projects (YIS). Documentation can be found here: Jira training for Yamaha IS Projects (YIS).
To monitor the progress for software development for SAP and Informatica related to the Yamaha Next Stage project issues need to to be manually linked on EPIC level between Yamaha Next Stage Project (EUYNS) and Yamaha IS Projects (YIS).
A YIS Epic can be linked to multiple epics in EUYNS.
...
Sub-tasks can be creation under the Story to break down the work done.
After creation of a YIS EPIC open the issue and create 3 Issue links via +
...
When opening
Jira | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|
In Big Picture PROG-13 is used for YNS Project overview.